(영문) 울산지방법원 2018.10.17 2018가단9073
대여금
Text

1. The Defendant: (a) KRW 200,000,000 for the Plaintiff and 5% per annum from October 28, 2017 to April 26, 2018.

Reasons

According to Gap evidence Nos. 1 and 2, it is recognized that the plaintiff lent 200 million won interest to the defendant on October 15, 2014 as of October 15, 2014 and as of October 15, 2015.

In addition, from November 14, 2014 to October 27, 2017, the Plaintiff recognized that the Defendant was paid interest of KRW 63 million in total over 36 times per month, namely, the amount of interest at least KRW 2 million.

According to the above facts of recognition, the Defendant is obligated to pay the Plaintiff a loan of KRW 200 million and damages for delay calculated by adding the rate of 5% per annum prescribed by the Civil Act to be sought by the Plaintiff within the scope of the agreement from October 28, 2017 to April 26, 2018, on which the copy of the complaint in this case was served to the Defendant, as requested by the Plaintiff, and 15% per annum prescribed by the Act on Special Cases concerning Expedition, etc. of Legal Proceedings from the next day to the day of full payment.

The plaintiff's claim of this case is accepted as all reasonable grounds, and the judgment in favor of the defendant is rendered.

Litigation costs shall be borne by the defendant.

A provisional execution shall be attached.

It is so decided as per Disposition by this kind.