logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울동부지방법원 2019.09.10 2019가단125233
구상금
Text

1. The Defendant’s KRW 31,023,156 and KRW 31,023,154 among the Plaintiff’s KRW 12% per annum from June 25, 2015 to January 31, 2016.

Reasons

1. If the purport of the entire argument is added to the evidence evidence Nos. 1 through 4 of the judgment on the cause of the claim, the Plaintiff entered into a credit guarantee agreement with the Defendant on June 17, 201, and issued a credit guarantee certificate setting the guarantee period of KRW 50,00,00 from June 17, 201 to June 16, 2016 with regard to the Defendant’s general loan of KRW 85,00,000,00,000, the credit guarantee amount of KRW 50,50,000,000 from the above bank as collateral, and the Defendant collected the principal amount of KRW 50,00,000 from the above bank as collateral, but on May 13, 2015, the Plaintiff’s subrogation interest rate of KRW 30,000,000,000 for the Defendant’s loan of KRW 50,000,000,0000,000.

According to this, the defendant is obligated to pay to the plaintiff 31,023,156 won (=31,031,904 won - KRW 8,750 won) and 31,023,154 won among them, 12% per annum, which is the rate of delay delay damages, from June 25, 2015 to January 31, 2016, which is the date of subrogation, 10% per annum, which is the changed rate of delay damages from the next day of the bill of this case until April 8, 2019, as the date of delivery of the copy of the complaint of this case, 15% per annum as prescribed by the Act on Special Cases concerning the Promotion, etc. of Legal Proceedings from the next day to May 31, 2019, and 12% per annum from the next day to the date of full payment.

2. The plaintiff's claim for conclusion is reasonable, and it is so decided as per Disposition.

arrow