Text
1. All of the instant lawsuits are dismissed.
2. The costs of lawsuit are assessed against the plaintiffs.
Reasons
1. Details of the disposition;
A. The Plaintiff B is the owner of G 119 square meters (hereinafter “instant land”) in Cheongju-si, Cheongju-si, and the Plaintiff C and D are the owners of each building on the ground of Cheongju-si, Cheongju-si (hereinafter “instant land 2,” and each of the said lands collectively “each of the instant lands”).
Location - Location of the project site: The type and name of the project site of I and I and the 322 lots of land: The name of the urban planning facility (Auniversity): the area or scale of the implementation of the project for five facilities, other than the new construction of a cultural hall: 467,92 square meters: - the area or scale of the project for five facilities: 467,92 square meters for each facility (scale) - the area (scale) for multi-purpose cultural hall, multi-purpose gymnasium, 2 playground, 2 playground, 2 playground, 2 playground, 370.47 square meters for the total ground area (scale) 16,723 square meters for the total ground area (area 1/6) 16,704 square meters (area 5 square meters on the ground of underground 2/ ground) and 16,756 square meters for the total ground area (area 5), 3,340 square meters (area 53,600 square meters for the period from the date of approval for completion of the completion of the project.
B. On June 3, 2005, at the request of the president of A.I.D., the Defendant approved the implementation plan of the project of the said project of the said school, culture center, etc. (hereinafter “the instant project”), and announced it to the public noticeF in Cheongju-si on the same day. The main contents are as follows:
(2) If the project execution period is changed from February 16, 2007 to December 31, 2008 to December 31, 2009 to December 31, 2009, the implementation plan was changed from December 31, 2009 to December 31, 2009 to December 31, 201, the implementation plan was changed from December 201, 201 to December 31, 201, the project execution period was changed from September 26, 2013 to April 26, 2013 to 46, 18, 205, 207.