Text
1. The Defendant’s KRW 316,234,017 as well as 6% per annum from October 15, 2018 to November 11, 2020 to the Plaintiff.
Reasons
1. Basic facts
A. On August 1, 2016, the Plaintiff concluded a construction contract (hereinafter “instant construction contract”) with the Defendant to conclude a contract with the construction cost of KRW 7,62,951,90 (hereinafter “instant construction”) from August 1, 2016, setting the construction cost of KRW 7,62,951,90, and the construction period from August 16, 2016 to October 9, 2017 (hereinafter “instant construction contract”).
The construction contract of this case changes over ten times, and the date of each contract, the changed construction amount, the extended completion completion plan, and the reasons for the change are as follows.
. Grounds for the 20.1.7, 62, 951, 900 of the initial contract date for the change of the total construction cost, August 1, 2016; 2. No change of the 1.22.1.28, 2017; 3. There is no change in the 1.28.28, 2017; 3. There is no change in the construction period due to the 1.6.6. 8. 7. 8, 2017’s change in the construction site; 4. 8. 1. 6. 8, 2062, 961, 900 of the 1. 7. 8. 86. 71, 2017; 4. 8. 1. 6. 7. 8, 2018 of the 1. 7. 8. 2018 of the 2016. 7. 206. 7. 2081. 2068
B. On July 31, 2018, the Plaintiff submitted an inspection of completion to the Defendant on July 31, 2018, and on September 14, 2018, the extension of construction to the Defendant.