Text
Defendant shall be punished by a fine of one million won.
However, the execution of the above punishment shall be suspended for one year from the date this judgment becomes final and conclusive.
Reasons
Punishment of the crime
The Defendant is a person who operates B(State), C(State), and D(State), and E is a person who produces sand using facilities such as machinery driving containers, etc. owned by the said companies or G(H) at a place of business located in F of the Chungcheongnam-gun, Chungcheongbuk-gun, and supplies it to the said companies.
On the other hand, on January 5, 2015, Cheongju District Court’s enforcement officers I attached to the said workplace a written notice to the effect that “as delegated by creditors G, the said workplace shall not transfer the said corporeal movables, establish the pledge right, or transfer the said possession to another person or alter the name of possession of the said corporeal movables or alter the title of possession of the said corporeal movables by the executor’s executor’s order of provisional disposition “the prohibition of possession, transfer and disposal of corporeal movables” with the executor’s executorial power of the said court’s 2014Kadan3657.”
Nevertheless, on May 2018, the Defendant and E conspired to remove the container by ordering the Defendant to E and accepting the direction of E.
Since then, in accordance with the above order of the Defendant, E, along with the J, etc., the employees of the above B (ju) from May 21, 2018 to May 30, 2018, as seen in “the part of the judgment on the Defendant’s assertion” under the above 1 container and the two of the electrical panel of the driving room electricity division at the above workplace. As regards “one unit of the hydroelectric voltager and one of the electrical panel of the driving room,” the Defendant’s side was confirmed to be owned by C Co., Ltd. operated by the Defendant through the decision of recommending reconciliation in the appellate court of civil litigation (an objection by the third party) brought against the above provisional disposition obligee, and the ownership or possession of the hydroelectric voltager, etc. after the lapse of the given period from May 21, 2018 to May 30, 2017, the Defendant or the provisional disposition obligee was drafted around August 20, 2017.