Text
1. The defendant's KRW 5,644,350 to the plaintiff A, KRW 26,030,80 to the plaintiff B, and KRW 9,638,450 to the plaintiff C, and each of them.
Reasons
1. Circumstances and results of appraisal of the ruling;
(a) Approval and announcement 1) Public-Private Partnership Project (D Project (Section 14) 2): The Seoul Regional Construction and Management Administration to which the defendant belongs, for E 3 project implementers announced by the Ministry of Land, Infrastructure and Transport on August 7, 2015;
B. The Central Land Tribunal’s ruling of acceptance 1 on June 8, 2017) subject to expropriation - Plaintiff A: The head of Sinsan-dong, Seoyang-gu, Incheon-si - Plaintiff B: 1,250 square meters in the Dong-dong, Seoyang-si, Seoyang-si, and H 72 square meters in the name of the Plaintiff C - Plaintiff C: one-2 shares in the amount of 1/2 shares in the amount of 168 square meters in the amount of 1,250 square meters in the amount of Goyang-dong, Seoyang-si, Seoyang-si, and one-2 shares in the amount of 169 square meters in the amount of 168 square meters in JJdo
(2) Compensation for losses: The date of commencement of expropriation: (a) the following [Attachment]’s “amount of adjudication for expropriation” is indicated: (b) the appraisal corporation; (c) one appraisal corporation; (d) one appraisal corporation; (e) Aion appraisal corporation (hereinafter “appraisal”) and one appraisal corporation (hereinafter “appraisal for expropriation”).
(c) The Central Land Expropriation Committee’s ruling on October 26, 2017 (1) and compensation for losses: 2) An appraisal corporation: A flood appraisal corporation and the Central Appraisal Corporation (hereinafter “Objection Appraisal”)’s appraisal result;
D. The appraisal result of this Court (hereinafter “court appraisal”) - The appraisal value: The appraisal value is as indicated below in the “court appraisal amount” column.
[Voting] The plaintiff's dismissal of the court's appraisal amount of AF 731,517,750 won (Dong) 737,162,100 won (Dong) G 87,250 won (Dong Dong) G 887,250,750 won (Dong Dong) 17,395,200 won (Dong) 17,676,000 won (Dong) 280,645,200 won total of KRW 904,645,676,676,000 won (Dong) 280,645,200 won (Dong) 2630,676,676,000 won (Dong 26,030,000 won) CI 563,100,250,250 won (Dong 2564,204,7465,467,204,75,294,20467,504,204,