(영문) 서울중앙지방법원 2014.04.10 2013가합501068
건물명도
Text

1. The plaintiff's claims against the defendants are all dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Basic facts

A. The first site owners and AH (hereinafter “the first site owners”) entered into a contract on August 2, 2002 with respect to construction works for which WW, X, Y, Z, AB, AB, AC, AD, AE, AF, AG, and AH (hereinafter “the instant site owners”) as the right holders of the ownership over the size of 1646m2, Seocho-gu Seoul Metropolitan Government AI (hereinafter “instant building site”), with their owner on August 2, 2002 and AJ Co., Ltd (hereinafter “AJ”) and AK apartment (hereinafter “instant building”) on the instant site up to September 30, 2003.

On October 14, 2002, the Plaintiff entered into a subcontract with AJ on December 31, 2003 with respect to the construction period for the structural frame of the instant building, and started new construction works on November 23, 2002.

B. AH transferred the ownership transfer registration for each of the instant shares to 1/16 shares on September 9, 2002 to AL, AM, Defendant D, A, and S. On September 9, 2002, AH transferred the ownership transfer registration for each of the instant shares to 1/16 shares. On September 17, 2002, AAE completed the registration for ownership transfer for 1/16 shares out of the instant shares to AP on October 4, 2002, WT completed the registration for ownership transfer for 1/16 shares out of 1/16 shares to 20.3 of the instant shares to 20.3 of the instant shares, and the ownership transfer registration for 1/16 shares to 20.3 of the instant shares to 1/16 shares to 20.3 of the instant shares, each of the instant shares was completed for 20/16.2 of the instant shares to 21/16.2 of the instant shares, each of the instant shares to 20.1/6.3 of the instant shares.