logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울중앙지방법원 2017.01.25 2016가단5129199
손해배상(기)
Text

1. The defendant shall pay 32,080,000 won to the plaintiff and 15% per annum from November 6, 2016 to the day of full payment.

Reasons

1. Facts of recognition;

A. On December 26, 2015, the Plaintiff (contractor) entered into a contract for the instant construction project with the Defendant (contractor) for the construction of the CP located in the wife population B (hereinafter “instant construction contract”). The main contents are as follows.

The scope of services that the Defendant is required to provide to the Plaintiff: C’s preparation of the manufacturing drawing, the construction and installation of container buildings in line with the manufacturing drawing, and the total construction permit agency contract amounting to 140,000,000 won necessary for the construction of buildings (in addition, it appears that the Plaintiff and the Defendant agreed not to pay an additional tax on the ground that the additional tax was separately concluded, but the tax invoice was not issued thereafter). The time of completion of construction: 0.3% of the contract amount;

B. The Defendant paid the Defendant KRW 149,000,000 (including the Rotterdam amount of KRW 9,000,000,000), including the contract price of the instant construction project, by March 30, 2016.

C. However, the Defendant did not complete the construction by the date of completion of the instant construction, and suspended the construction.

Since the Defendant’s construction of this case’s construction of this case’s construction of the construction of this case’s main outer wall, installation of the wall surface of the first floor, installation of the wall surface of the second floor warehouse, disposal of the second floor board of the first floor toilet, and non-working of the bottom space of each floor of the first floor container, etc., the Plaintiff requested 13,000,000 won and completed the construction of this case’s construction of this case’s construction of this case’s construction of this case’s construction of this case’s construction of this case’s construction of this case’s construction of this case’s construction of this case’s construction of this case’s construction of this case’s construction of this case’s construction of this case’s construction of 13,00,00

[Reasons for Recognition] Each entry of Gap evidence Nos. 1 through 13 (including each number), witness D's testimony, the purport of the whole pleadings

2. Judgment on the plaintiff's claim

A. According to the above facts, the defendant's construction contract is the defendant's total damages amounting to KRW 22,00,000,000.

arrow