(영문) 대전지방법원 2016.05.04 2012구합3073
손실보상금
Text

1. The defendant is 880,003,608 won to the plaintiff limited liability company A, 491,108,500 won to the plaintiff limited liability company B, and 483,117,488 won to the plaintiff limited liability company C.

Reasons

1. Details of ruling;

A. Business title 1) Business title: D Construction Project (hereinafter “instant project”).

2) Project operator: Defendant 3 Notice: E notified by the Ministry of Land, Transport and Maritime Affairs on June 29, 2009, and notified by the Ministry of Land, Transport and Maritime Affairs on February 10, 2010.

B. Land subject to expropriation by the Central Land Expropriation Committee on December 16, 2011 (hereinafter “Adjudication of Expropriation”): Each land listed in the attached Table 1 List Nos. 24 through 28 shall be classified into the land [Attachment 1 List Nos. 24 through 28] of G forest 49,587 square meters at the time of permanent residence prior to the division (hereinafter “G land prior to the division”) and the land divided into H forest 119,929 square meters at the time of permanent residence prior to the division (hereinafter “H land prior to the division”).

[) Of the plaintiffs' "owners" (hereinafter collectively referred to as "owners' shares"), the shares in the plaintiffs' "land A" (hereinafter collectively referred to as "land A", and when indicating individual land, it shall be indicated in the same way as "I land" according to its lot number): 2. On February 8, 2012: An appraisal corporation: an appraisal corporation substituted by an appraisal corporation, a central appraisal corporation, a compensation for losses (excluding the plaintiff's G land before division, a claim for the remaining land expropriation, a claim for the purchase of soil and rocks collection stations, and a claim for the establishment of factory relocation measures) for the plaintiff A (hereinafter referred to as "Plaintiff A"): 60,719,720 won: Plaintiff B:521,971,270 won, and Plaintiff C:496,310 won, 2496,310 won.

C. Plaintiff B: (a) the Central Land Expropriation Committee made an objection on June 22, 2012 (hereinafter “Objection”) No. 1) Plaintiff B: 524,279,670 won: Plaintiff C: 245,127,210 won, excluding the remaining 14,428 square meters and the remaining 11,95 square meters, excluding the area of 14,428 square meters incorporated into the business site among G land before subdivision; and (b) the area of 111,974 square meters, excluding the area of 14,95 square meters incorporated into the business site among H land before subdivision, is larger, and is used for the previous purpose due to the instant project.