Text
1. All of the plaintiff's claims are dismissed.
2. The costs of lawsuit shall be borne by the Plaintiff.
Reasons
1. Details of the disposition;
A. The Plaintiff submitted a report on employment maintenance training, temporary retirement, and temporary suspension of employment as shown in the attached Form 2 employment maintenance plan on the ground that the demand for semiconductors has decreased due to global financial crisis and physical competition erosion, which is an inevitable situation in which the adjustment of employment is inevitable, as a manufacturer of multilateral, transpers, and similar semiconductor elements.
B. As to the period of employment maintenance measures from December 7, 2008 to June 30, 2009, the Plaintiff filed an application for employment maintenance support with the Defendant after filing a report on the same content as the attached Form 2 employment maintenance measures plan, and between July 20, 209 and October 14, 2009, the attached Form 1 disposition list is as between July 20, 2009 and October 14, 2009.
The application for the payment of the workplace childcare subsidy, childcare leave subsidy, and wage for the preservation of wage peak system was made in part of the site level of the subsidy, etc.
C. On June 26, 2009, the Defendant received the Plaintiff’s report on the illegal receipt of employment maintenance support payment (hereinafter “the instant report”) and conducted an investigation into whether the Plaintiff’s application for employment maintenance support payment is appropriate, such as ascertaining the fact that the Defendant informed the person subject to employment maintenance measures from June 29, 2009 to November 30, 209.
On July 3, 2009, 6, and 31 of the same month, the Plaintiff notified the Defendant that 10 of the persons subject to employment maintenance measures had been on overseas business trips during the period of application for employment maintenance measures as shown below, and filed an application for refund, and filed an application for correction of the cases for which 10 of the persons subject to employment maintenance measures had been granted subsidies.
[Attachment 1] The date of application for correction of the annual application details and the date of application for refund request / The period of application for the type of voluntary report date from December 15, 2008 to December 21, 2008 (7 days) to December 23, 2008 (24 February 24, 2009) shall be paid on July 312, 2009 to July 5, 2009.
1. 11 (day) no later than 11 January 2009
1. Payment date of overseas business trip ( April 30, 2009) No. 3 C Training on July 31, 2009 between January 5, 2009
1. 11 (7 days) January 2009