(영문) 서울중앙지방법원 2016.04.29 2015가단5054410
용역비
Text

1. The Defendant’s KRW 88 million and its KRW 12 million among the Plaintiff’s KRW 22 million from May 26, 2010 to KRW 22 million.

Reasons

1. Basic facts

A. The Plaintiff is a company with the main purpose of developing computers and related hardware, software development, etc., and the Defendant is an advertising agency business, an Internet, and an information and communications service provider.

B. On August 3, 2009, the first contract B between the Defendant and the Nonparty Company B (hereinafter “B”) concluded a “C contract” (hereinafter “the first contract”) with the Defendant with respect to the supply and technical support of mobile brush with respect to the supply and support of mobile brush.

- Contract amount: 1.39 billion won (including value-added tax) - Contract period: from August 3, 2009 to November 28, 2009 - Delivery and Development Schedule 1) owned by the Defendant, as of the date of conclusion of the contract, the period of completion of the provision of API and the provision of technical human resources shall be August 3, 2009. 2) B B financial FPD mobile slab (Win CE 5.0, Win 6.1) and the supply of each baler file and soft code of the WE 5.0) based on the TFD base (in CE 5.0) and the MU code shall be provided until September 1, 2009.

3) After the completion of the provision of paragraphs (1) and (2) above, the Defendant shall implement technical assistance as to the above products and results to B until November 20, 2009, and detailed details shall be based on a separate statement of technical assistance. 4) 1) as to the time when the Defendant’s technical personnel deemed to require technical assistance or B becomes the employees of B as of November 25, 2009. However, the Defendant shall obtain the consent of employment for the human resources employed under B by the time of the conclusion of this contract. (c) The period of contract for technology transfer between the Plaintiff and the Defendant : the contract for technology transfer - the contract amount: 240 million won (excluding value-added tax, hereinafter the same shall apply).

- Article 2 (Scope of Contracts) - The Plaintiff shall conduct technology transfer to B during the term of contract as follows:

(1) Two persons, including the head of the D team, shall be B.