사기등
A defendant shall be punished by imprisonment for one year.
However, the execution of the above punishment shall be suspended for two years from the date this judgment became final and conclusive.
Punishment of the crime
To the extent that there is no concern about substantial disadvantage to the defendant's exercise of his/her right of defense, rhythizing the facts charged without changing the indictment and recognizing the facts charged.
The defendant is a person who has been engaged in livestock breeding business with the trade name of D in Gyeong-si.
1. The project for modernization of livestock facilities from the National Treasury subsidies (Violation of the Subsidy Management Act, Fraud) is a national subsidy project supported by 20% (on the basis of the Special Act on Assistance to Farmers, Fishermen, etc. following the Conclusion of Free Trade Agreements and the Livestock Industry Act (on the basis of a special Act on Assistance to Farmers, Fishermen, etc.) and 20% (on the basis of a subsidy), 30% (on the basis of a subsidy), 50% (on the basis of a subsidy), and 50% (on the basis of the annual interest rate of 3
In addition, the above business shall allocate national subsidies to each Metropolitan City/Do with funds, such as new construction, reconstruction, renovation, and repair of livestock pens, etc., and the Metropolitan City/Do shall examine livestock farmers deemed eligible for national subsidies from the Si/Gun and select livestock farmers to be provided with national subsidies, and shall grant subsidies through each Si/Gun.
On February 11, 201, the Defendant submitted an application for the modernization project of livestock pens facilities with the total project cost of KRW 560,00,000 (subsidies of KRW 167,067,000, loans of KRW 278,460,000, and KRW 114,473,000), which is for remodeling D's livestock pens, at the office of the Sinyeong-si 225, Seogyeong-si, Park Jong-si, the Defendant was selected as a person eligible for support for the modernization project of facilities in 2011, on June 21, 2011, the Defendant additionally selected as a person eligible for support for the modernization project with the total project cost of KRW 515,930,00 (subsidies of KRW 151,200,000, loans of KRW 263,930,00, KRW 100,800).
After being selected as a person eligible for additional subsidy, the Defendant changed the total project cost from 515,930,000 to 504,000,000 won (subsidies 151,200,000, 252,000,000, and 100,80,000,000,000) on December 19, 201, following the change in the decision to grant a stable facility modernization project in 201.