집행정지
2019 Asia 12195 Suspension of Execution
1. A stock company;
2. B;
Minister of Oceans and Fisheries
Busan Port Corporation
December 24, 2019
1. The disposition taken by the respondent to select an intervenor as a priority negotiating entity in relation to the development project of the Class C (Stage 2) of the Busan Port Area (Stage 2) and the Class 1 harbor hinterland complex shall be suspended from its effect until the 30th day after the judgment of the case on the selection of a priority negotiating entity was rendered by this Court 2019Guhap 75266.
2. The applicant's remaining requests are dismissed.
Except for cases where suspension of execution is sought not later than the final and conclusive date of the judgment in this Court No. 2019Guhap75266, the same as the order
According to the results of the examination and the explanation of the applicant's submission, it is recognized that there is an urgent need to prevent the applicant from suffering irrecoverable damage due to the execution of the disposition stated in the order, and there is no other data that can be deemed that suspension of execution may seriously
The applicant's application shall be accepted within the scope recognized by the main text of paragraph (1), and the remainder of the application shall be dismissed as it is without merit. It is so decided as per Disposition.
December 24, 2019
presiding judge, judge Park Jong-yang
Judges Park Jong-hwan
Judge Lee Professor