Text
1. The Defendant: (a) KRW 40,000,000 for the Plaintiff and 15% per annum from December 15, 2018 to May 31, 2019; and (b) the Plaintiff.
Reasons
The Plaintiff lent a total of KRW 40 million to the Defendant until September 20, 2009, and the Defendant agreed to pay the Plaintiff a total of KRW 100,000 per day from February 2, 2010 to the Plaintiff does not conflict between the parties, or the Plaintiff’s agreement to pay the Plaintiff a total of KRW 10,000 per day is acknowledged based on the overall purport of the pleadings in
According to the above facts, since the period of repayment for the above borrowed loan has arrived, the defendant is obligated to pay to the plaintiff the amount of 40 million won of the borrowed loan and the damages for delay calculated at the rate of 15% per annum as stipulated in the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings before the Amendment from December 15, 2018 to May 31, 2019, as requested by the plaintiff, following the delivery day of the copy of the complaint in this case, as the plaintiff demanded after the due date.
As to this, the defendant alleged to the effect that he paid part of the borrowed money to the plaintiff, but there is no evidence to acknowledge it.
Therefore, the plaintiff's claim of this case is reasonable, and it is so decided as per Disposition by admitting it.