(영문) 창원지방법원통영지원 2016.08.24 2015가단24842
손해배상(기)
Text

1. Defendant B’s 48,801,934 won and the interest rate of 15% per annum from June 5, 2016 to the date of full payment.

Reasons

1. Claim against the defendant B

(a) the description of the reasons for the claim and the changed reasons for the claim;

(However, “Defendant 1” and “Defendant D” are “D,” “Defendant 2” as “Defendant B,” and “Defendant 3” as “Defendant C Co., Ltd.”

Judgment by deeming the confession based on recognition (Article 208 (3) 2 and Article 150 (3) of the Civil Procedure Act)

2. The plaintiff, as to the defendant C, filed a claim for damages against the defendant C on the ground of a tort, and the plaintiff first filed a claim for the construction payment against the defendant C. However, since the claim against the main defendant Eul is accepted in full, the plaintiff's claim against the main defendant C is dismissed. It is so decided as per Disposition by the assent of all.