logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 춘천지방법원강릉지원 2015.04.21 2013나1706
공사대금
Text

1. Of the judgment of the court of first instance, the Defendant-Counterclaim Plaintiff, the amount of which exceeds the amount ordered to pay the principal claim in the following manner:

Reasons

1. Basic facts

A. The Plaintiff, who is running a business by using the name of J Construction or K Construction without a license, as well as the current status of retaining and retaining walls, is the Plaintiff’s land D, L, M, N, andO (hereinafter “instant construction site”) owned by the Defendants.

(A) Of the construction works of a pentent, a retaining wall (hereinafter referred to as “instant retaining wall”) shall be placed on the said land from June 22, 2012 to July 2012, 2012.

) Civil engineering works such as installation, etc. (hereinafter “civil engineering works of this case”)

(2) The Plaintiff conducted the instant retaining wall only with concrete construction of the instant retaining wall, and completed it at the site of the instant civil engineering work, and the finishing construction was completed after the Defendant’s steel completion at the Plaintiff’s construction site.

3) Of the instant construction site, the retaining wall of this case was located in four sections as follows (hereinafter referred to as “A, B, C, and D” in order to order the retaining wall A, B, C, and D. (hereinafter referred to as “the retaining wall A, C, and D”).

(B) On August 2013, the D section collapses after typhoons have passed. (B) The method of payment and payment of the construction cost of the instant civil construction cost was reported to the designated parties B and paid the cost of the instant civil construction cost by the means of reporting the actual cost to be paid each day by the Plaintiff to the designated parties B and receiving the relevant cost by proxy.

In other words, the Plaintiff entered the construction cost required in the process of performing the instant civil works on a daily basis and confirmed by the selector B, and received the payment confirmed as above from the selector B to the post account in the name of the Plaintiff at the time of confirmation.

2) The construction records prepared by the Plaintiff (Evidence A No. 3, hereinafter “instant books”)

(3) In the above process, the Plaintiff’s daily details are included in the instant book from June 22, 2012 to June 30, 2012, from July 2, 2012 to July 5, 2012, and from July 9, 2012. 3) The Selection Party B confirmed the above-mentioned book and confirmed the said book from June 22, 2012 to July 8, 2012.

arrow