Text
1. The defendant shall pay 51,090,000 won to the plaintiff and 15% per annum from April 3, 2018 to the day of complete payment.
Reasons
1. Basic facts
A. At the Defendant’s request, the Plaintiff invested the Plaintiff’s construction equipment at the site of Sungju-si and C works from June 1, 2016 to December 4, 2017.
B. On January 11, 2018, the Defendant prepared and delivered to the Plaintiff a letter of intent to pay KRW 51,090,000 for the above equipment cost, but did not pay the above equipment cost up to now.
[Identification Evidence] Facts without dispute, Gap evidence Nos. 1, 2, and 3, the purport of the whole pleadings
2. According to the above facts of determination, the Defendant is obligated to pay to the Plaintiff the equipment cost of KRW 51,090,000 and damages for delay calculated at the rate of 15% per annum from April 3, 2018 to the day of full payment, which is the day following the delivery of the original copy of the instant payment order, to the day of full payment.
3. In conclusion, the plaintiff's claim is reasonable, and it is so decided as per Disposition by admitting it.