(영문) 인천지방법원 2015.09.02 2015가단38162
물품대금
Text

1. The Defendant’s KRW 37,00,000 as well as 6% per annum from August 19, 2014 to June 8, 2015 to the Plaintiff.

Reasons

1. The Plaintiff is engaged in the wholesale and retail business of fishery products under the trade name of “C”, and the Defendant was supplied with fishery products from around 2012 to August 18, 2014 by the Plaintiff, and the Defendant prepared and made a payment note that the Plaintiff shall pay KRW 37 million to the Plaintiff around August 18, 2014, based on the overall purport of the evidence No. 1, and evidence No. 2-1, as well as the entire arguments. The Defendant is obligated to pay the Plaintiff damages for delay calculated annually from August 19, 2014 to June 8, 2015 by the day after the date the Plaintiff was supplied with the unpaid goods price of KRW 37 million and fishery products from the Plaintiff.

2. In conclusion, the plaintiff's claim of this case is reasonable, and it is so decided as per Disposition with the plaintiff's claim.

arrow