1. Defendant B, each of whom indicated in the separate sheet No. 1 to 10, and 1, is indicated in the separate sheet No. 1,421 square meters before Namyang-si, Namyang-si.
Reasons
1. Basic facts
A. Defendant C is the land category of the E-owned land in Namyang-si, Namyang-si, and its size was 4,179 square meters, but was 3,982 square meters in division on March 29, 198.
The owner was the owner of the land of G from F on December 5, 1987 for the traffic between the land of the above E and the public service, but the land category of G was “land” on February 6, 2001, but it was “factory site” on February 6, 2001. Although the area was 2,876 square meters, it became 2,053 square meters in the division on July 15, 1999, but became 2,053 square meters in the division on July 15, 199, and was 527 square meters in the division on August 19, 199, and became 1,807 square meters in the division on September 7, 199 and became 1,520 square meters in the division on February 6, 201.
The land category of the land on the D is referred to as the “electric field,” and the area is 1,421 square meters.
Among them, approximately 40 square meters were purchased in 2,00,000 and the price was paid in full, and possession and use was transferred about 40 square meters among the above G land and the above D land as a road.
B. On October 29, 198, the Plaintiff purchased approximately KRW 40,000 among the above land E and the above land G and the above land D from Defendant C, and paid the price in full. On December 30, 1989, the Plaintiff completed the registration of ownership transfer on the above land E and approximately 40,000 out of the above land E and the above G land and the above D land, and occupied and used approximately 40,000 of the above land as dry field, and approximately 40,000 of the above land and the above D land as roads.
(Specificly, H from around 191 to the present date, with the Plaintiff’s consent, passes between the said land and the said land via approximately 40 square meters among the said land and the said D land.
F The F completed the registration of ownership transfer on July 21, 1997 following the sale of the above G land to I on July 16, 1997, and ② the registration of ownership transfer was completed on July 6, 1998 following the donation of the above D land to Defendant B, a child, on July 6, 1998.
F receives to Defendant C the payment of approximately KRW 2,00,000 for approximately 40 square meters out of the Plaintiff’s above land E and the above G land and the above D land on December 28, 1987 and the above D land on December 28, 1987. The payment of KRW 2,00,000 for approximately 40 square meters out of the above D land is made in the future. The above G land and the above D.