(영문) 전주지방법원 2019.05.02 2018가합2287
설계용역비
Text

1. The Defendant’s KRW 605,960,587 to the Plaintiffs, as well as 5% per annum from June 9, 2018 to May 2, 2019.

Reasons

1. Basic facts

A. On July 28, 2016, the Defendant (competent D University) announced that the contract price was KRW 88,330,000,000 of the basic and shop design documents, etc. (hereinafter “instant service”) with respect to the new construction of E (total construction cost was KRW 17.41 billion, including the initial value-added tax; hereinafter “instant construction work”).

(F) Notice of D University; hereinafter “Public Notice of this case”). Chapter VII Other relevant matters

3. If it is necessary to revise or supplement a design by integrating the matters pointed out by the Examination Committee and the requirements of the ordering department, the ordering agency shall revise and supplement the plan intermediate working design time and reflect it in the design; b) the ordering agency may require the designer to consult on and revise the details of the success at the time of the plan, intermediate or working design, and the winner shall reflect the matters requested by the ordering agency in the design;

C) The ordering authority may require the winner to seek advice and review from relevant experts on matters necessary for the basic and working design, and shall reflect the result in the design. (e) The design service contractor may not require additional service costs due to an increase in the total construction cost after the completion of the working design.

4. The winner shall, upon being notified of the fact that he/she has been selected as the winner, promptly consult with the ordering person on the design contract within the publicly announced design amount. (f) If the winner does not correspond to the design service cost calculated according to the Government budget Bill, the guidelines for preparing a draft fund management plan and the construction cost, etc. and makes an unreasonable demand for the design service cost, the election may become invalidated

Detailed matters concerning the instant service at the time of the public announcement of the instant public announcement of the tender refer to the guidelines for public offering of new construction design for E (hereinafter “instant guidelines for public offering of design”).