logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 수원지방법원 2016.03.31 2013가합23054
손해배상(기)
Text

1. The defendant shall attach to the plaintiffs each money recorded in the "request amount" column in the separate sheet and each of the above money.

Reasons

1. Basic facts

A. The Defendant’s implementation of road works and the acquisition of the land owned by the Plaintiffs (hereinafter “previous project”) paid compensation to the Plaintiffs as indicated in the following table, and acquired land owned by the Plaintiffs (hereinafter “each of the instant land”).

The compensation for the ownership transfer of land (won) shall be 54 square meters per 54 square meters per 12,825,000 square meters per 12,825,00 on May 3, 2000, E, 106 square meters per 106 square meters per 106 square meters per 24,115,000 on October 5, 2000, F. 22,950,000 square meters per 102 square meters per 1,950,000 on June 5, 2000; 23 square meters per 1,350,000 on June 5, 200, 200, 300 square meters per 23 square meters per 175,000,000 on June 5, 200, 3, 200, 15 square meters per 106,537,58 square meters per 205 square meters per 37.

B. On June 30, 2004, the Minister of Construction and Transportation, on the part of the Ministry of Construction and Transportation, designated a single unit of land, such as NA, P, Q, etc., as a “R housing site development area,” under the notification of the Ministry of Construction and Transportation on December 30, 2005. (2) On December 30, 2005, the Minister of Construction and Transportation, under the notification of the Ministry of Construction and Transportation, changed the name of the said planned unit of land into “M housing site development area,” and the project implementer, under the existing Gyeonggi-do Governor, the head of the Gyeonggi-do, the head of the Suwon-do and the head of the Gyeonggi-do local public corporation,

(C) The Minister of Construction and Transportation, on June 28, 2007, partially changed the location, size, etc. of the instant project and approved the approval of the modification of the instant project and the implementation plan to the public notice of the Ministry of Construction and Transportation. (4) Each of the instant land is included in the instant project site.

【Ground of recognition】 The fact that there is no dispute, entry of Gap Nos. 1 and 2 (including each number), and the purport of the whole pleading

2. Occurrence of liability for damages;

(a) for the original public service upon occurrence of the redemptive right;

arrow