Text
1. The Defendant shall pay to the Plaintiff KRW 121,705,50 and the interest rate of KRW 15% per annum from November 8, 2016 to the date of full payment.
Reasons
1. In full view of each statement in Gap evidence Nos. 1 through 9 (Evidence Nos. 1, 2, and 4 was forged, but no evidence exists to acknowledge it) as to the cause of the claim, the plaintiff entered into a construction contract with the defendant around November 28, 2015 with regard to the portion of the creative steel construction among the defendant and the smuggling B, with the price of KRW 1,90,000 (Additional Tax Table), the period from December 1, 2015 to February 29, 2016; ② the part of the construction contract and additional contract under the above contract were completed by the plaintiff, but the defendant paid KRW 121,705,50 among the construction price promised by the defendant, respectively.
According to the above facts of recognition, the Defendant is obligated to pay the Plaintiff the amount of KRW 121,705,500 unpaid construction cost and the damages for delay calculated at the rate of 15% per annum as stipulated in the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings from November 8, 2016 to the date of full payment following the delivery of the copy of the claim and the application for modification of cause of this case, as the Plaintiff seeks.
2. The plaintiff's claim for conclusion is justified, and all of them are accepted.