(영문) 의정부지방법원 2019.10.30 2019가합50472
부당이득반환
Text

1. The defendant shall pay to each plaintiff listed in attached Tables 2 through 5, and the payment amount of the attached Tables 2 through 5.

Reasons

1. Basic facts

A. (tentative Name) The F Regional Housing Association is an organization organized to promote the establishment, etc. of the regional housing association that implements the business of supplying newly-built apartment houses with G members of the Namyang-si, Namyang-si, and the said organization obtained authorization to establish the regional housing association at the Namyang-si, by applying for authorization to establish the regional housing association at the Namyang-si.

【As the rights and obligations of the F Regional Housing Association are comprehensively succeeded to by Defendant F Regional Housing Association, the following shall be collectively referred to as the “Defendant Association.”

From October 6, 2015 to December 15, 2016, the Plaintiffs entered into an agreement to enter into an association with the Defendant Cooperative (hereinafter collectively referred to as “each of the instant agreements to enter into an association,” and each of the instant agreements to enter into an association. The key contents of the documents submitted by the Plaintiffs to the Defendant Cooperative at the time of entering into each of the instant agreements to enter into an association are as follows.

[Written Consent of the Project Plan] The contractor himself under this Agreement is aware that the said Project Plan may be modified or adjusted at the time of construction deliberation, approval of the Project Plan (or amendment), commencement of construction and occupancy, and that no civil or criminal objection shall be raised against the revised or adjusted Project Plan, and that no objection shall be raised against all civil or criminal charges even if the number of units and units are modified according to the circumstances of the progress in the purchase of land in the future (a confirmation) and submission of the written Consent of the Project Plan to the Defendant Union.

(6) Under this subscription contract, the contractor himself/herself shall be aware that he/she may change or adjust the plan of business, the plan of funds, the scale of business, etc. at the time of approval of the project plan, and shall not raise any objection, and the number of such units shall be somewhat reduced depending on the future authorization, permission, and purchase of land.