logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 광주지방법원 순천지원 2013.10.24 2012고단3332
명예훼손
Text

The defendant is innocent.

Reasons

1. The summary of the facts charged was that the Defendant had subcontracted the “G Civil Works (hereinafter “the instant construction”) within the F Industrial Complex (hereinafter “the instant construction”) from the victim D (the age of 64) who operated the (State)C on December 1, 201, and had been performing the construction work under a subcontract from the said victim’s D (the age of 64). However, the Defendant did not complete the construction work until February 10, 2012, which was the contract term, and did not go against the victim’s termination on the ground that the defective construction was performed.

1. The fact of defamation caused by sending content certification was that the victim paid the construction cost to the defendant according to the progress rate of construction work, and the victim did not unilaterally pay the progress payment, and the victim did not demand that the defendant prepare 20 million won at the personnel expenses of the ordering person. In addition, the construction work was delayed for more than one month because the defendant failed to properly prevent water from running in the section where the defendant intended to perform construction by the soften sk sk sk sk sk sk sk sk sk sk sk sk sk sk sk sk sk sk sk sk sk sk sk sks

Nevertheless, around March 13, 2012, the Defendant agreed orally at the expense of the victim at the personnel cost of the ordering person after completing the “accommening from a State I Office located in H, and from the “accommening the content” in the title of “accommening the content,” which is run by the Defendant.

The victim did not pay progress unilaterally and did not know that he did not pay progress payment.

The delay in the payment of progress payment by the victim C is due to delay in the payment of progress payment, and I did not pay it within a reasonable time, and the construction was temporarily suspended due to the failure to procure equipment and materials, and there is a lack of decision of the ordering person, and the construction cost has not yet been suspended and the subordinate construction has not yet been finished.

arrow