Text
1. The Defendant’s KRW 627,722 as well as the Plaintiff’s annual rate of KRW 5% from October 13, 2017 to January 14, 2020, and the following.
Reasons
Basic Facts
On June 2017, the Plaintiff was awarded a contract for basic construction works, reinforced concrete construction works, machinery and equipment works, and electrical and telecommunications construction works among the instant construction works, which were executed by the Defendant on the ground of the Defendant’s racing market (hereinafter “instant construction works”).
From June 21, 2017, the Plaintiff commenced the instant construction and completed the construction around September 29, 2017, and the Defendant completed the registration of ownership preservation on the 99.75 square meters of reinforced concrete structure hybrids, which was completed in accordance with the instant construction on October 12, 2017.
[Based on the recognition] The facts without dispute, Gap evidence Nos. 1 and 2, Eul evidence Nos. 1, and Eul evidence Nos. 1, and the plaintiff's assertion that the plaintiff asserted the purport of the whole pleadings, the construction cost to be paid by the defendant upon completion of the construction in this case shall be KRW 1.45 million for the basic construction cost (1.9 million for the original construction cost, but only KRW 1.45 million for the original construction cost), KRW 1.45 million for the marina sand, KRW 1.355 million for the marina sand, KRW 52 million for the construction cost for reinforced concrete (1.4 million for the construction cost for ready-mixed and steel Nos. 52 million for the above construction cost). Thus, even if the defendant paid the above materials cost, the full amount of the construction cost for the above reinforced concrete shall be paid), KRW 3.6 million for the construction cost for the machinery and equipment, and KRW 6.290,000 for the purification cost, etc.
(A) The Plaintiff, while setting the construction cost for electricity and telecommunication as KRW 4.2 million, was directly paid by the Defendant, was excluded from the claim amount). The Plaintiff, among the instant construction works, served as the site manager for the remaining portion except the Plaintiff’s entrusted construction works and received the remuneration of KRW 5.0 million per month.
Accordingly, the Plaintiff, among the instant construction works, has completed the basic construction works and reinforced concrete construction works contracted by the Defendant, and performed its duties for one month from August 28, 2017 to September 29, 2017 as the site manager for one month. As such, 500,000 won for one month from among them.