(영문) 서울남부지방법원 2019.08.22 2018가단220349
대금반환
Text

1. The defendant,

A. From May 19, 2018 to August 22, 2019, Plaintiff A, as well as KRW 83,00,000.

Reasons

1. Facts of recognition;

A. The Plaintiff Co., Ltd. (hereinafter “Plaintiff Co., Ltd.”) is a company that produces images and advertises on behalf of the parties, and the Plaintiff Co., Ltd. is the representative director of the Plaintiff Co., Ltd., and the Defendant is a company that produces safly, etc. using 3D printers, and D entered into an agency contract with the Defendant as the spouse of Plaintiff B, and operated the Defendant’s agency (Nog datum).

B. On June 7, 2017, the Plaintiff Company entered into a sales agency contract with the Defendant with the content that the right to sell more than KRW 111,000,000 (including value-added tax and expenses for negligence) was paid to the Plaintiff Company and the Defendant (hereinafter “instant sales agency contract”) at KRW 111,00,000 for the contract price (hereinafter “instant sales agency contract”).

(2) At the time of the above contract, the Plaintiff Company and the Defendant agreed on June 20, 2017 on the commencement date of sales of the goods and July 20, 2017 on the delivery date of the goods.

3) Of the above contract price of KRW 111,00,000, 23,000,000, the Plaintiff Company and the Defendant shall substitute the sales revenue of the U.S. Pursuant to the U.S. Pursuant to the contract amount of KRW 23,00,000,000, the Defendant shall pay to D the Defendant a total of KRW 17,000,000,000,000, out of the remainder of KRW 71,000,000,000, excluding this, was agreed to pay the Defendant the remainder of KRW 71,000,000,000 until June 7, 2017.

5) Meanwhile, on April 30, 2019, D transferred KRW 23,00,000 to the Plaintiff Company the claim for sales revenue of the foregoing U.S. C. A contract between Plaintiff B and the Defendant on August 29, 2017 between Plaintiff B and the Defendant with the authority to sell KRW 20,200,000 for contract price (i.e., product price of KRW 20,000,000 for negligent program cost).