(영문) 서울고등법원 2015.04.22 2013나57919
손해배상 등
Text

1. Of the judgment of the first instance court, the part against the Defendants in the judgment is modified as follows.

Defendant 1.

Reasons

1. Basic facts

A. The Plaintiff is the party’s position 1) The Plaintiff is the party’s household of 201 apartment-type factories 481-4, Geumcheon-gu, Seoul, Geumcheon-gu (hereinafter “instant building”).

(2) In order to manage the building, Defendant KID Entertainment Co., Ltd. (hereinafter “Defendant KI”) is a project proprietor who constructed and sold the building of this case, and the wall mountain construction Co., Ltd. (hereinafter “ wall mountain construction”) was decided on July 3, 2012 by Seoul Central District Court Decision 201 Gohap116, Jul. 3, 2012; hereinafter “ wall mountain construction”) is a contractor who purchased the building of this case from Defendant KI to construct the building of this case, and the Defendant Construction Mutual Aid Association is a corporation that entered into a warranty contract for the building of this case and the building of this case.

B. The warranty period from March 23, 2009 to March 22, 2010, including the 116,810,339 and lighting works, to March 22, 2010, shall be 292,025,8473 designated from March 23, 2009 to March 22, 201, and the following three-dimensional bearing walls from March 23, 2009 to March 22, 201, and from March 22, 2012, from March 23, 2009 to March 22, 200, 620, 4 containers, roof, and waterproof period from March 23, 200 to March 21, 205 to March 23, 2015 to March 22, 2013; and the mutual aid association of this case from March 23, 2015 to March 22, 2013.

(2) Of the guarantee terms and conditions (hereinafter “instant guarantee terms and conditions”) stated in the said warranty terms and conditions, the part related to the instant case is as follows.

Article 1 (Guarantee Liability) Defendant Construction Mutual Aid Association has undergone the inspection of use or inspection of new construction of the building of this case.