logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 부산지방법원 2016.06.15 2014가합13825
공사대금
Text

1. The Defendant’s KRW 105,128,247 as well as 6% per annum from October 17, 2014 to June 15, 2016 to the Plaintiff.

Reasons

1. Basic facts

A. On July 3, 2013, the Plaintiff received from the Defendant the “A factory extension construction project” on the ground B of Ulsan-gun, Ulsan-gu, Ulsan Metropolitan City (hereinafter “instant construction project”) by setting the construction cost of KRW 1,870,000 (including value-added tax; hereinafter the same shall apply) and the construction period of KRW 5,70,000 (including value-added tax; hereinafter the same shall apply) from July 5, 2013 to December 31, 2013.

B. On July 29, 2013, the Plaintiff and the Defendant agreed to exclude the cost of construction from the cost of fire-fighting system installation (hereinafter “the first modified contract”) and reduced the cost of construction to KRW 1,822,75,000 (hereinafter “the first modified contract”), and on June 18, 2014, the cost of construction increased to KRW 1,853,16,700 (hereinafter “the second modified contract”). The final construction cost is the amount calculated by adding the amount of KRW 1,502,647,00 (excluding value-added tax) paid to the comprehensive construction (ju) as of June 15, 2014) to KRW 225,00,00 (excluding value-added tax).

- the liquidated damages and the final settlement of the additional construction costs;

3. A (State) shall pay the fire-fighting contract amount of KRW 42,950,00,00 (value-added tax separate) entered into with the General Bonded Construction Co., Ltd., by June 27, 2014, to A (State) after completion of payment by June 27, 2014 in the International Bonded Construction Co., Ltd., and submitted by the Vice-General Construction Co., Ltd., to A (State) after obtaining written confirmation of the completion of deposit from the UN.

6. A written consent to direct payment issued by the Korea-Japan General Construction Co., Ltd. in April 1, 2014 shall be withdrawn by June 18, 2014 and shall be submitted to A (State) with a written confirmation from the foregoing East Electricity.

7. Civil petitions received by the Construction Association shall be withdrawn by June 18, 2014.

8. The Han average Construction (State) must complete all the construction works, including fire fighting construction, in good faith in accordance with design drawings and specifications, and the completion of the construction shall be by June 30, 2014.

9.If this Agreement does not comply, the second modified contract between A (State) and Korea-China Comprehensive Construction (State) shall be null and void.

C. On June 18, 2014, the Plaintiff and the Defendant concluded the instant construction project at the time of concluding the said secondary amendment agreement.

arrow