(영문) 전주지방법원 2017.07.07 2014가단42914
공사대금
Text

1. The Defendant’s KRW 52,130,873 as well as the Plaintiff’s annual rate of 5% from February 11, 2014 to July 7, 2017, and from July 8, 2017.

Reasons

A. The Plaintiff entered into a subcontract with respect to the instant framework construction (hereinafter “instant framework construction”) among the new construction works, and the main contents are as follows. In the event that the Plaintiff said the subcontracted framework construction works, the Plaintiff entered into the subcontract with respect to the instant framework construction works.

[Standard Subcontract Agreement for Construction Business] Construction : The construction site of the pelvis-gu D Construction on June 6, 2013 and the contract price on December 10, 2013 on completion of the construction works at the Jeonju City: The rate of compensation for delay: 0.1% for delay * The present Corporation shall make a single contract * The Plaintiff shall make all the materials to be adjusted to the amount of the construction contract by up to 95%, and shall be submitted along with the following documents:

* Parties enter into a contract for construction works in accordance with the above contents and the separate contract terms of construction works, one design drawings, and one specifications, as well as one specifications.

The attached or expanded part of a fair sheet shall be approved with the contractual unit price.

* Process Schedule of Aggregate Construction (No. 1-3) was drawn up for 125 days after the commencement of construction work on underground floor, 1-9 floors and 125 days after the commencement of construction work on rooftops.

【Conditions of Special Contract for On-Site Explanation (Alley)】

2.The contractor shall, if necessary, extend, reduce or night work in accordance with the order of the contractor in accordance with the work progress, and any increase in the construction cost resulting therefrom shall not be recognized as being included in the original unit price. 3. Special priority points in the contract 3-1. Fairness 1.) The contractor shall comply with the process, such as the schedule of work, attached hereto.

3-3. Quality Section 1) To ensure the quality of steel tanks to the extent that it is possible to carry out dynasing operations, and to use the materials corresponding thereto; 3).