(영문) 대전지방법원 2015.01.28 2014고단1379
사기등
Text

A defendant shall be punished by imprisonment for three years.

Reasons

Punishment of the crime

The Defendant of "2014 Highest 1379" was a person who had substantially operated C (State) and (State)D; around March 7, 2007, the Defendant entered into a contract to purchase the land of 5,283 square meters and all of the steel structure (hereinafter the instant real estate) of the Daejeon Seo-gu E and four lots of land outside Daejeon from the construction of Posco and paid the down payment of 1.6 billion won; the 6th class below ground, the 46th class above ground, the total floor area of the building, approximately 95,70 square meters; the 100 billion won project cost; and the person who promoted the new construction project of the collective housing.

1. On May 2007, the Defendant entered into a contract to purchase the instant real estate from the Posco Construction for the purpose of the instant apartment complex project, i.e., the Defendant, at the 5th floor D office of the Seo-gu Daejeon Daejeon, for the purpose of the instant apartment complex project, with the Defendant selected the Si Construction and received a payment guarantee from the Military Mutual-Aid Association and received a payment guarantee from the company, in full payment of the PF funds and received a transfer of ownership.

First of all, the steel frame installed to carry out the removal of steel shall be estimated to be approximately 4,00 tons per kilogram and to be recovered by directly treating the steel frame after completion of the removal work and deducting 400 million won after the completion of the removal work, but first of all, 200 million won shall be the performance bond.

7. By the time of 30.30, the removal work will be commenced, and if the removal work has not been commenced until then, the amount of the deposit will be the compensation.

8. up to 30. Payment

Along on the 8th day of the same month, a contract for removal of steel frame was concluded with the victim.

However, at the time of fact, only one billion won of the down payment was paid to the Kitco Construction.

arrow