(영문) 대전지방법원 2016.01.06 2015가단28613
대여금
Text

1. The Defendant shall pay to the Plaintiff KRW 62,00,000 and the interest rate of KRW 15% per annum from July 2, 2015 to the day of complete payment.

Reasons

1. In addition to the purport of the entire pleadings in the statement of evidence No. 1, it is recognized that the Defendant borrowed from the Plaintiff the sum of KRW 15 million, KRW 15 million, KRW 15 million, KRW 29 million, and KRW 69 million, whichever is later, on July 1, 2010, and the Defendant prepared and issued a certificate of borrowing that the Defendant would pay the Plaintiff the full amount of KRW 69 million until July 3, 201, and thereafter, the Defendant paid the Plaintiff KRW 7 million.

2. According to the above facts, the Defendant is obligated to pay to the Plaintiff the remainder of the borrowed amount of KRW 62 million (=69 million - seven million) and delay damages calculated at the rate of 15% per annum under the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings from July 2, 2015 to the date of full payment, which is the day following the delivery of the instant complaint sought by the Plaintiff.

Therefore, the plaintiff's claim of this case is justified and it is so decided as per Disposition.