Text
1. The defendant shall pay to the plaintiff the amount of KRW 80,802,468 and KRW 80,033,865 from January 3, 2019 to the date of full payment.
Reasons
1. In full view of the purport of the entire pleadings, the facts of recognition as to Gap evidence Nos. 1 through 6 (including each branch number, if any), the defendant received a loan (hereinafter referred to as "the loan contract in this case") by setting the lending period of KRW 184,880,00 from E Co., Ltd. (hereinafter referred to as "E") on June 21, 2016 as 72 months, the lending interest rate of KRW 7.3% per annum, the overdue interest rate of KRW 24% per annum, 24% per annum, and Eul transferred the above lending claim against the defendant to the plaintiff on April 6, 2018, and around April 10, 2018, the above notification was delivered to the defendant as the debtor on or around April 10, 2018, and on the other hand, the fact that the defendant delayed the payment of the loan in installments with only a part of the above lending debts and the remaining principal of KRW 80,383,39639,975 won,437.
2. According to the determination and conclusion, the Defendant is obligated to pay to the Plaintiff the total amount of KRW 80,802,468 (=80,033,865 Won 73,698 Won 34,905 Won) and damages for delay calculated at the rate of 24% per annum, which is the overdue interest rate for the loan contract of this case, as to the remaining principal.
Therefore, the plaintiff's claim is reasonable, and it is decided as per Disposition.