(영문) 의정부지방법원 2016.09.23 2016가단110024
공사대금
Text

1. The Defendants shall jointly and severally serve as KRW 90,000,000 on the Plaintiff and as a result, from June 30, 2016 to September 23, 2016.

Reasons

1. The description of the grounds for the claim shall be as specified in the attached Form;

(A) The Plaintiff is claiming damages for delay from the date of delivery of the duplicate of the instant complaint. Since the maturity date of the instant agreement is May 30, 2016, the Defendants are liable for delay from May 31, 2016 to the date of delivery of the duplicate of the complaint. Since the date of delivery of the duplicate of the instant complaint to the Defendants is June 30, 2016, damages for delay can be acknowledged at the rate of 5% per annum from the date of delivery (see Articles 208(3)1 and 257 of the Civil Procedure Act).