(영문) 부산지방법원 2020.01.10 2019구합23266
주거이전비 등
Text

1. All of the plaintiffs' claims are dismissed.

2. The costs of lawsuit are assessed against the plaintiffs.

Reasons

Details of the disposition

Plaintiff B (D) is the child of E (F) and G (H) is the wife of E.

Plaintiff

A (I) The birth of E is the birth of E, and J (K) is the birth of the plaintiff A.

Defendant C Housing Redevelopment and Improvement Project Association (hereinafter “Defendant Cooperatives”) is a Housing Redevelopment and Improvement Project Association established to carry out housing redevelopment and rearrangement project (hereinafter “instant rearrangement project”) within the area of 54,289 square meters of Seoul Southern-gu L (hereinafter “instant rearrangement zone”).

On February 27, 2008, the remaining head of Busan Metropolitan City, including the public inspection and announcement of the improvement zone and the designation of the improvement zone, set the public inspection period from February 27, 2008 to March 14, 2008 for the designation of the improvement zone of the rearrangement zone of this case, and made public inspection and announcement of the designation of the improvement zone of this case to residents and interested parties.

On June 18, 2008, the head of the Nam-gu Busan Metropolitan City designated an improvement zone by N-ro publicly notified by Busan Metropolitan City, and changed the maintenance plan and the improvement zone on March 16, 2016.

On December 23, 2016, the Defendant Cooperative received authorization to implement the instant rearrangement project implementation (hereinafter referred to as “authorization to implement the instant project”), from the head of the Nam-gu Busan Metropolitan Government, to construct multi-family housing (multi-family housing) and ancillary and welfare facilities (hereinafter referred to as “instant authorization to implement the project”), and the head of the Nam-gu Busan Metropolitan City publicly announced on December 28, 2016.

The registration of ownership transfer based on sale on the same day in the name of E on March 26, 1988 with respect to cement block structure slives and 58.18 square meters (hereinafter “the instant housing”) located in the Busan Southern-gu Seoul-gu Seoul-gu Seoul-gu Seoul-gu improvement zone for the change of the owner of the instant housing, and the registration of ownership transfer based on sale on August 27, 2019 was completed in the name of R on September 17, 2019.

Plaintiffs.