(영문) 서울중앙지방법원 2016.09.06 2016가단55514
사용료
Text

1. The defendant shall pay to the plaintiff KRW 55,259,713 and KRW 36,168,085 among them, from April 6, 2016 to the day of full payment.

Reasons

1. Indication of Claim: On January 17, 2013, the Plaintiff entered into a contract for automobile facility leasing with the Defendant for the lease fee of KRW 1,008,420 per month, KRW 36 months, interest rate of delay rate of KRW 24% per annum, and KRW 5,259,713 as of April 5, 2016 under the said automobile facility leasing contract (i.e., remaining obligation of KRW 36,168,00 interest rate of KRW 1,233,70 interest rate of KRW 5,464,094, KRW 286, KRW 234,00 per annum, and KRW 2,107,60 per annum, and the Defendant has lost its interest due to delay in the payment of the lease fee at least twice. Thus, Article 238(3) of the former Civil Procedure Act (i.e., payment of the principal due to delay in the payment of the unpaid principal by public notice.