(영문) 광주지방법원 순천지원 2015.12.30 2015고단1114
업무상과실치사등
Text

The Defendants are not guilty.

Reasons

Summary of Facts charged

1. Defendant B and Defendant A, around October 201, intended to newly construct a 4 heat plant to E located in Mineyang-si, and contracted the construction of the above heat plant to F and G Co., Ltd. (hereinafter “this project”). The F and G Co., Ltd completed the installation and installation of the 4 heat plant around November 2013, and C had a trial run for the normal operation of a factory (hereinafter “this construction trial”).

Defendant

A is the general manager of this project, who is in charge of safety and health management related to this project, and Defendant B is the supervisor for this project operation from the head of the dry Operation Team.

The business owner shall not assign dangerous work such as flammable oil or ignitable scrap or dangerous substance to containers such as pipes, tanks, drums, etc. which are likely to cause dangerous substances, unless he/she takes measures for the prevention of explosion or fire, such as removal of inflammable or inflammable objects other than dangerous substances, or removal of dangerous substances, etc.

Of the project, three smoke plant (factory that gives pressure to metal scrap, which is a liquid metal scrap) uses a high-tension oxygen to remove foreign substances on the surface of the steel board, and in the event there are inflammable substances such as maintenance portion in high voltage oxygen pipes and valves, etc. or foreign substances, explosion is likely to occur due to heat, etc. in the process of contact with high voltages in high voltages, around May 30, 2014, it is found in the valves installed near the 3 smoke plant (facilities that remove foreign substances on the surface of the steel board using high voltages) and re-cleaning work after being found in the valves installed in the washing process (facilities that remove foreign substances on the surface of the steel board using high voltages). Since then, on June 3, 2014, it is located near the junium plant located near the 3st gun plant.

arrow