(영문) 서울남부지방법원 2013.07.16 2012가합6975
손해배상 등
Text

1. The Plaintiff’s lawsuit against Defendant Il Young-young Co., Ltd.: ① KRW 1,022,13,659 and its amount of KRW 584,806,163.

Reasons

1. Basic facts

A. Status 1 of the parties concerned) The Plaintiff is the Young-si A Apartment (hereinafter referred to as the “instant apartment”).

(2) The Defendant M&C Co., Ltd. (hereinafter “M&C”) is a project proprietor who constructed and sold the instant apartment, and Defendant Shin Young-young Co., Ltd. (hereinafter “M&C”) is a new construction contractor of the said apartment.

3) Defendant Housing Guarantee Co., Ltd. (hereinafter “Korea Housing Guarantee”)

(B) On April 2, 2010, Defendant Il Young-young entered into a contract for the repair of defects (hereinafter “instant warranty contract”) as indicated below, with the guarantee creditor as to the instant apartment between Defendant Il-young and the housing guarantee company on April 2, 2010, on the following (hereinafter “the details of the contract for the repair of defects”) and the contract for the repair of defects (hereinafter “instant warranty contract”). When referring to each of the above warranty contracts, the contract for the repair of defects (hereinafter “instant warranty contract”).

[Attachment Table of Contract for Repair of Defects] No. 1012120-201-004201 April 16, 2010 through 173,012, 012, 007 201-201-201-404202, 205, 205.16.20, 205, 205, 201-16 and 430, 205, 205, 205, 205, 205, 205, 205, 205, 205, 205, 205, 205, 205, 205, 205, 2015, 205, 205, 2015, 201-4, 204, 2014, 205, 2014.

C. Regarding the apartment of this case