1. The Defendant’s KRW 110,000,000 and its amount shall be 15% per annum from May 9, 2019 to May 31, 2019 to the Plaintiff.
Reasons
1. Claim for the payment of the “solar power generation facility works among the C New Construction Works,” the construction of which was subcontracted by the Defendant on May 20, 2017, and the performance of the claim for damages for delay.
2. The portion of the partial dismissal of claims that exceeds the amount calculated by the ratio of 12% per annum with respect to the principal from among damages for delay after June 1, 2019 (the amendment of the provisions on statutory interest rate under the main sentence of Article 3 (1) of the Act on Special Cases Concerning Encouragement, etc. of Legal Proceedings)
3. Article 208 (3) 1, and Article 257 (1) of the Civil Procedure Act of the applicable Act.