logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 춘천지방법원 2017.01.19 2015고정205
재물손괴
Text

The defendant shall be innocent.

Reasons

1.1. At present, the parts of the defects shall be repaired up to 1st to 5th floor, and the parts of the defects shall be treated as soon as possible through drawings and specifications. If the defects shall be handled at will by the owner of the building and the cost of the defective repair shall be calculated by requesting the specialized institution to reduce the cost of the construction.

2.The payment method of the Corporation shall be made by means of a loan of financial rights after completion of the Alley project.

3. Materials to be paid to the project owner shall be collected and deducted from the construction cost; and

In addition, F is responsible for all materials, and the construction is resumed after the re-contract is drawn up.

The late compensation shall be notified by the date of preparation of the re-contract or by the date of submission of a written waiver.

4. At the time of discontinuance of construction at least five (5) days due to F’s failure to meet the requirements for termination in entirety until August 2012, F waives the construction, and waives the lien, and the construction cost will be a civil criminal liability in the event of failure to perform the commitments after completion. * Additional Construction cost: : KON-based PON-based PON-based (hereinafter “F”) calls for the payment of the remainder of the construction cost in this case at the time of failure to complete the Round PON-based construction from among the 30 million Won CY-based construction work, and the instant construction was suspended around August 31, 2012. Since KON-based PON-based (hereinafter “NON-based”) demanded F to complete the construction from around that time, but F did not comply with the demand of F to complete the construction, the instant construction was terminated on November 29, 2012, and the instant construction was not completed by 2012.

“A notice was given to the effect that the said notice reached F at that time, and if the facts were to be the same, the instant contract was lawfully terminated in accordance with the F-based notice of termination on November 29, 2012, on the grounds of the F-based default on obligations.

F. F. F. F. as set out in the letter of agreement of this case.

arrow