(영문) 청주지방법원 2015.05.21 2014구합10528
손실보상금
Text

1. The Defendant: (a) 22,527,80 won to Plaintiff A; (b) 22,527,800 won to Plaintiff B; (c) 7,181,300 won to Plaintiff C; and (d) 7,181.

Reasons

1. Details of ruling;

(a) recognition and public announcement of a project - H district development project - Public announcement of H district development project - Public announcement of H district development project: on December 16, 201, the designation of a H district urban development zone and the approval of a development plan (I public announcement of Chungcheongbuk-do): Defendant;

(b) The adjudication on expropriation by the competent Land Tribunal of Chungcheongbuk-do on June 18, 2013 - The land to be expropriated and the compensation shall be as follows:

(1) The land to be expropriated shall be as follows: (a) CK 169,316,360 won (217,480 won or less) D 169,360 won (217,480 won or more) D 169,316,360 won or 460 won (217,480 won or more) E L2,479 (647,019,000 won or more) 647,019,000 won or more (261,500 won or more) and 842,40,750,000 won or more, or 169,316,360 won or more (217,480 won or more); (b) 2,479,019,000 won or more (261,000 won or more); and (c) 3,500,740,000 won or more of G242.

(c) The Central Land Expropriation Committee’s ruling on April 17, 2014 - Contents of the ruling: The entries in Table 2 below:

In Table 2, the difference between the appraised value of the appraisal value of the owner's lot number (land size): J 1,543 372,248,750 won - 373,251,700 won 1,002,950 won B 372,248,750 won - 373,251,700 won 1,002,950 CK 1,871 169,316,360 won - D 169,360 won - E 2,479,019,000 won - FM 8421,000 won - 425,78,740,750 won - 460,750,747,758,740, 57,760, 57, 507, 407, 467, 507

2. The assertion and judgment

A. The amount of compensation for losses caused by the plaintiffs' assertion acceptance ruling and objection ruling was wrong in selecting comparative standards or not proper comparison of goods.