logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 대구지방법원 2019.07.19 2018가합2251
공사대금
Text

1. The Defendant’s KRW 192,50,000 and the Plaintiff’s annual rate of KRW 6% from February 2, 2019 to June 5, 2019, and the following.

Reasons

1. Basic facts

A. The Plaintiff is a company engaged in stone construction business, stone processing and sales business, and the Defendant is a company engaged in building work business, engineering work business, etc.

B. On February 1, 2018, the Plaintiff entered into a subcontract with the Defendant: (a) with respect to tiny works among the new construction works of Daegu-gu and two lots of ground D officetels, the construction period from March 1, 2018 to May 30, 2018; and (b) entered into a contract to change the construction period from March 1, 2018 to August 30, 2018 to KRW 247,50,000 (including value-added tax; hereinafter the same shall apply); and (c) concluded a contract to change the construction period from May 30, 2018 to August 31, 2018 to KRW 275,00,000.

(hereinafter “instant first construction contract”). C.

On June 18, 2018, the Plaintiff entered into a subcontract with the Defendant, setting the construction period of tin works from June 19, 2018 to August 31, 2018, and the construction cost of 165,000,000 won, among the new construction works on the land of the Daegu-gu and six parcels of land (F), and entered into a contract to change the construction cost of 192,50,000 won on the ground of the additional construction works on November 22, 2018.

(hereinafter “instant second construction contract”). D.

The Plaintiff completed all of the instant construction works under the instant first and second construction contracts; (1) from the Defendant, with respect to the instant construction contracts, KRW 50,00,000 on June 1, 2018; KRW 50,000,000 on June 25, 2018; KRW 20,000 on July 4, 2018; and KRW 60,000 on August 13, 2018; KRW 00,000 on September 22, 2018; KRW 00,000 on September 13, 200; KRW 10,000 on December 13, 2018; and KRW 10,000 on December 14, 208; and KRW 30,000 on August 30, 200, respectively; and

[Reasons for Recognition] Facts without dispute, entry of Gap evidence 1 to 5 (including each number), the purport of the whole pleadings

2. According to the above facts of determination as to the cause of the claim, the defendant is the plaintiff among the construction cost of KRW 275,00,000 under the contract of the first construction project of this case.

arrow