(영문) 수원지방법원 2016.05.25 2013구합20159
손실보상금
Text

1. The Defendant’s KRW 13,400,000 as well as annual 5% from September 11, 2013 to May 25, 2016 to the Plaintiff.

Reasons

1. Object of the trial;

A. The record of this case reveals the following facts.

1) The Plaintiff filed the instant lawsuit against the acceptance ruling stating that “the amount of compensation for the land burial shall not be determined as KRW 12,180,000, and no compensation for livestock farming business losses shall be determined.” The Plaintiff asserted in the complaint that “the calculation of compensation for business losses is unlawful.” As part of the compensation, the Plaintiff sought payment of KRW 1,00,000 as compensation. As to the obstacles thereafter, the court’s appraisal results on which the total amount of KRW 21,68,368,360, which is less than KRW 12,180,000, which is less than KRW 13,400,000, and KRW 21,668,368,360, which is more than KRW 12,180,000, KRW 12,000, KRW 90, KRW 368,000, KRW 360,000, KRW 368,360,080, or00.

(2) On November 17, 2015, the purport of the claim was extended to seek payment of the total amount of KRW 13,400,000 according to the court appraisal, and the purport of the claim was further expanded. (2) On November 5, 2015, the Defendant stated that the Plaintiff withdrawn the claim for compensation regarding obstacles through the Plaintiff’s request for modification of the purport of the claim and cause of the claim on November 17, 2015, on the grounds that the Plaintiff withdrawn the claim for compensation regarding obstacles on November 17, 2015.

B. According to the above facts, the Plaintiff filed a claim for compensation for business losses at the warden. On October 13, 2015, the Plaintiff set the claim amount by deducting the excessive amount of compensation in the expropriation ruling regarding the defective goods compensation amounting to KRW 13,400,000, out of the claim amount and the application amount for modification of the cause of the claim as of October 13, 2015, but extended the claim amount by seeking the total amount of the claim amount of the business compensation claim as of November 17, 2015.

Therefore, the claim of October 13, 2015 is sought.