Text
1. The Plaintiff:
A. Defendant B Co., Ltd. shall be KRW 67,500,000 and the year from August 6, 2015 to August 25, 2016.
Reasons
1. The facts of recognition [1] On April 1, 2013, Defendant B Co., Ltd. (formerly: D Co., Ltd.; hereinafter “Defendant Company”) concluded a contract for construction works on three lots, including E and Daegu-gu, for construction works for building on the ground (hereinafter “instant construction works”) on three lots, including E and Daegu-gu, KRW 1.55 million, the commencement date, April 10, 2013, and December 31, 2013.
On September 11, 2013, the Plaintiff and the Defendant Company entered into a subcontract for construction works (hereinafter “instant subcontract”) with respect to the creative, metal, and miscellaneous construction works among the instant construction works, with the construction cost of KRW 137.5 million (including value-added tax, advance payment of KRW 30 million, and payment in cash after completion), the construction period from September 10, 2013 to October 30, 2013.
[2] On September 11, 2013, the Plaintiff received advance payment of KRW 30 million from the Defendant.
After receiving advance payment, the Plaintiff continued the construction, but the construction was suspended due to the dispute between the Defendant Company, such as the termination of the contract on November 26, 2013 by E, the owner of the construction, and the lawsuit between E and the Defendant for the return of the construction cost is pending.
On September 27, 2013, the Plaintiff paid KRW 10 million to G, and KRW 1.5 million to H on December 4, 2013, 200, and KRW 1.5 million to H on January 29, 2014, KRW 1.1 million on May 8, 2014, KRW 3.85 million on May 8, 2014, and KRW 3.8 million to J on July 15, 2014, KRW 4.8 million on June 5, 2015, and KRW 1.5 million on May 28, 2014, KRW 3.3 million on May 200, KRW 20035 million on May 3, 2014, and KRW 3.5 million on June 25, 2014, respectively.
On September 30, 2013, the Plaintiff entered into a contract for the supply of Jyoung Chang-ho and Fire-Fighting Co., Ltd. for the execution of the instant subcontract. However, the Plaintiff was unable to pay the price in full, following the Daegu District Court Decision 2014Da20988, No. 2015Na8269, the Plaintiff’s 31,954.