(영문) 창원지방법원마산지원 2017.09.13 2014가합1904
용역비
Text

1. The Defendant’s KRW 583,709,950 for the Plaintiff and 5% per annum from July 18, 2014 to September 13, 2017.

Reasons

1. Facts of recognition;

A. The Defendant is a rearrangement project association that obtained authorization for establishment from the Changwon-si mayor on March 19, 2012 under the Act on the Maintenance and Improvement of Urban Areas and Dwelling Conditions for Residents for the purpose of housing redevelopment improvement project (hereinafter “instant project”) whose project implementation district covers 67,582 square meters in Yongsan-si B, Changwon-si.

Article 2 (Period of Service) The period for performing design service shall be from the date of conclusion to the date of completion of approval for use.

Article 3 (Scope of Services)

A. The duties commissioned by the Defendant to the Plaintiff are as follows:

1) 2) 2) 3) 4) 4) 5) 1) 66 - 10 - 10 - 10 - 10 - 10 - 10 - 6 - 10 - 5 - 10 - 6 - 10 - 10 - 10 - 5 - 10 - 6 - 10 - 10 - 7 - 7 - 10 - 5 - 7 - 10 - 10 - 5 - 10 - 10 - 5 - 10 - 10 - 5 - - 10 - 10 - 10 - 5 -- 10 -- 10 -- 10 -- 10 -- 5 -- with 10 -- 5 ---- with respect with respect with respect for design and construction supervision.