(영문) 부산지방법원 2014.12.05 2013가합19956
임차료
Text

1. The Defendant’s KRW 238,807,585 as well as the Plaintiff’s annual rate from December 14, 2013 to December 5, 2014.

Reasons

1. Basic facts

A. On December 23, 2011, the Plaintiff refers to the installation of a provisional facility and the demolition of a provisional facility as a whole between the Defendant and the Defendant’s articles of incorporation 728 A-2 block, the front line of the Busan District captain-gun’s articles of incorporation, 728 A-2 block, which generally refers to the installation of a provisional facility and the demolition of a provisional facility. As a result, the Plaintiff is called as the dismantling of a provisional facility by integrating the installation of a permanent facility and the installation of a visual beam beam beam and a horizontal sloping beam beam in a horizontal and vertical line. When a concrete structure was built after the ground-breaking was completed according to the installed provisional facility, it would be called the dismantling of a provisional facility in order from the backline in which the installation of a provisional facility was installed.

However, among the earth boards installed by cutting off the ground in the edge of a building in a string file or in a successive order, part of the earth boards should play a role of soil prevention during the construction period, so it is not dismantled and buried as president without dismantling it.

(2) The construction period of construction 1,518,00,000 won from December 23, 201 to April 22, 2012 (i.e., the supply price of KRW 1,380,000,000 for labor cost of KRW 138,000 for value-added tax of KRW 138,000 for value-added tax of KRW 100,000 for each contract (hereinafter “instant contract”). On April 18, 2012, each of the instant contract entered into a subcontract (hereinafter “instant contract”). A subcontract to modify the construction termination period of the instant contract from April 22, 2012 to May 15, 2012, and again did not modify the subcontract price of each of the instant construction works from May 15, 2012 to July 31, 2013 (hereinafter “instant contract”).

나. 한편, 원고는 2011. 12. 21. 주식회사 퀸스틸(이하 ‘퀸스틸’이라고만 한다)과의 사이에 퀸스틸로부터 에이치빔(H-BEAM) 합계 약 800,000kg 을 4개월 기준 임대단가 1톤 당 13만 원(부가가치세 별도), 기간 연장시의 임대단가 1톤/1개월 당 3만 5,000원(부가가치세 별도),...