logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 창원지방법원 2017.10.26 2016가합1519
건물인도 등
Text

1. The defendant delivered the real estate stated in the attached list to the plaintiff, and the defendant delivered the real estate to the plaintiff, ② KRW 174,572,194, and the above money.

Reasons

1. Indication of claim;

A. On July 30, 2015, the Plaintiff entered into a lease agreement (hereinafter referred to as “instant lease agreement”) stipulating that the lease deposit of KRW 150,000,000, monthly rent of KRW 18,700,000 (including value-added tax) and the lease term of KRW 18,700,000 (including value-added tax) between July 11, 2015 and July 10, 2017, the Plaintiff leased real estate (hereinafter referred to as “instant real estate”) as indicated in the attached Table with the Batech Co., Ltd. (hereinafter referred to as “Batech”) and the Defendant around April 20, 2016, and the Plaintiff consented to the said sub-lease.

B. The Plaintiff terminated the instant lease agreement on November 14, 2016 on the grounds of the delinquency in rent of Natech, and thus, the Defendant did not deliver the instant real estate to the Plaintiff despite its duty to deliver it to the Plaintiff.

C. Therefore, the Defendant: (a) delivers the instant real estate to the Plaintiff; (b) jointly with the Natech, jointly with the Plaintiff, has the obligation to pay damages for delay calculated at the annual rate of 15% as stipulated in the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings from July 14, 2017 to March 8, 2017; (c) the expenses for restitution of the instant real estate; (d) KRW 17,241,210; and (e) the amount of unpaid electricity charges of KRW 16,920,640; and (e) the amount of unpaid electricity charges of KRW 174,572,194; and (e) the amount of damages for delay calculated from July 7, 2017 to July 14, 2017; and (e) the amount of damages for delay calculated at the rate of 15% per annum from July 14, 2017 to the date of complete payment; and (e) the amount of damages for delay.

2. Article 208 (3) 2 and Article 150 (3) of the Civil Procedure Act of the judgment deemed to be a confession.

arrow