logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 청주지방법원 2015.06.03 2014가합1642
공사대금
Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Basic facts

A. On July 18, 201, the Plaintiff entered into a contract with the Defendant for the manufacture and installation of production equipment and ethyl metal equipment, steel structure (production facility installation), mooring works, process pipes and ethyl pipeline works, steel dryp pipes works, removal of dryp equipment, etc. (hereinafter referred to as “first construction”) with the Defendant during the construction period of KRW 5,50,00,00 (value-added tax separate), from July 18, 201 to December 31, 201 (hereinafter referred to as “new construction contract”), with the Defendant for the construction period of KRW 20,000 for the construction cost of KRW 50,00,000 (value-added tax separate), from July 18, 201 to December 31, 201 (hereinafter referred to as “construction contract”). The construction contract was concluded with the Defendant for the construction period of KRW 20,000 (production 10,000,000) construction cost of the instant construction contract between September 29 and the Defendant 29.

B) Around September 20, 2012, the Plaintiff completed the instant construction work, and the Defendant paid the Plaintiff KRW 6,798,000,000 for the instant construction work (i.e., KRW 5,500,000 for the first construction work, KRW 618,00,000 for value added tax of KRW 618,00 for the second construction work, KRW 680,000 for the first construction work). [Grounds for recognition] The fact that there is no dispute, KRW 2 (including the provisional number, hereinafter the same shall apply)

of the witness B, the testimony of the witness B, the purport of the whole pleading

2. The assertion and judgment

A. On August 21, 2012 after the conclusion of the instant contract, the Plaintiff’s assertion is as follows: (a) between the Defendant and the lower court on August 21, 2012: (b) the construction of floor-to-land and pipeline; (c) the manufacture and installation of steel products from the outdoor storage tanks; (d) the removal of CGM equipment; and (5) the second floor.

arrow