(영문) 서울고등법원 2016.06.03 2015누45191
과징금납부명령취소
Text

All of the plaintiff's claims are dismissed.

Costs of lawsuit shall be borne individually by each person.

Reasons

1. Facts based on which there is no dispute over the details of the relevant facts and dispositions (based on recognition), Gap 1, 2, 13 (including provisional numbers), and the purport of the whole pleadings;

A. The Plaintiff’s status as the Plaintiff, Dongbu Construction Co., Ltd., and Koul Global Co., Ltd. (hereinafter “stock company”) are omitted, and the said three construction companies are those engaged in construction business as prescribed by Article 2 subparag. 1 of the former Monopoly Regulation and Fair Trade Act (amended by Act No. 11119, Dec. 2, 201; hereinafter “Fair Trade Act”).

(1) The construction project is to extend the installation and incineration of the sewage treatment plant to the outside of the construction project (a) the installation and incineration of the sewage treatment plant to the outside of the building project. The construction project is to build a leisure facility to the outside of the project site in the outside of the project site in the outside of the project site in the outside of the Chungcheongnam-gun, the outside of the project site in the outside of the project site.

The main construction works of the Public Procurement Service (Demand Agency) ordering construction works (to be extended to the installation and incineration of leisure facilities of the clean sewage treatment plant) - the design period for industrial and environmental facility works, such as the construction of leisure facilities, the construction of incineration facilities - the construction of a management Dong construction: 70 days from the date of the on-site explanation - the design of the basic design and the working design for the first construction: 70 days from the date of the date of notification of the selection of the person qualified for the working design - the weight of the method of selecting the successful bidder for the daily package deal tender (design 70%, price 30%) in the environmental office at the Cheongju-si Office, Cheongju-si, the government procurement agency (including value-added tax) or the public procurement agency, which is the ordering agency, has announced the tender announcement on December 11, 2009, the summary is as follows:

(2) According to the public tender notice of December 11, 2009 by the Public Procurement Service, which is the person ordering the bidding method and bidding procedure (A) tender procedure, each construction company submitted a prior examination of participation in bidding (hereinafter referred to as “PS examination”) document on December 18, 2009, and tender was conducted on March 9, 2010.

As a package deal design and construction project, 70% of the design score and 30% of the price score.