logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 대전지방법원천안지원 2017.06.23 2015가합102982
공사대금
Text

1. The Defendant-Counterclaim Plaintiff (Counterclaim Defendant) KRW 236,218,272 against the Plaintiff (Counterclaim Defendant) and the Plaintiff’s counterclaim from December 25, 2015 to June 23, 2017.

Reasons

A principal lawsuit and a counterclaim shall be deemed simultaneously.

1. Basic facts: The Defendant, the contractor, and the Plaintiff B’s construction period: On June 20, 2012, the date of completion of the construction of the additional construction works and the supplementary construction works on July 31, 2012, the date of completion of the construction work on February 17, 2012: KRW 425 million (Plaintiff B) shall prepare and provide a tax data (receipt, etc.) agreed with the certified tax accountant.

The method of payment for the construction cost (payment in installments according to the process): 50 million won (time of commencement): intermediate payment - the amount of 50 million won: 50 million won: Consultation - Any balance: 325 million won (construction work, etc.) shall be performed in accordance with the terms and conditions of this contract and design documents (including design drawings and estimates) and the terms and conditions of a side contract shall be responsible for the remainder after completion inspection.

(2) After completion, the studio 4, 2studio 2, 3rd floor and the studio studio are completed for construction to separate the studio from the main studio.

Provided, That the construction period of four parking lot studio may be postponed by one year after mutual consultation, and the construction cost shall be the number specified in the design drawings.

In such cases, the approval shall be deferred from the total construction cost and the parking lot shall be used as a parking lot by extending the ceiling and floor construction.

(3) Survey costs, including costs of survey, electricity, urban gas, and water supply installation costs for each household.

Article 12 (5) (5) "B" shall not delay or suspend the construction after the commencement of the construction work without any justifiable reason, and if the construction is not completed within the construction period, a delay compensation equivalent to 1/1,000 of the remaining construction work shall be paid to "A" in accordance with the number of delayed days, and such compensation shall be deducted from the construction cost.

A special engineer is subject to consultation with the owner of the project, and this contract is subject to reflection at the time of design and execution (consultations).

2. Internal finishing - The installation of a studio studio 2 studio-longing rooms - The studio north of the studio of the first floor is a bendro-long;

A. The Plaintiff A on January 20, 2012

arrow