(영문) 부산지방법원 2015.07.09 2014가합10772
임대료
Text

1. The Defendant (Counterclaim Defendant) construction of the Plaintiff (Counterclaim Defendant) Company A, 195,392,918, and the Plaintiff (Counterclaim Defendant) interesting construction.

Reasons

1. Basic facts

A. The Plaintiff A and the Defendant’s lease agreement 1) Plaintiff A and the Plaintiff Hean Heavy Construction (hereinafter “Plaintiff Company”).

) The construction machinery is a construction machinery business operator who leases construction machinery, such as strings, and executes construction directly by contract. The Plaintiff B is the representative director of the Plaintiff, and the Defendant and the Plaintiff Co., Ltd. (hereinafter “D”).

2) On April 23, 2013, as follows, D entered into a Offset period lease contract with the Defendant (hereinafter “instant suspended period lease contract”) and leased it to the Defendant on April 23, 2013. On April 23, 2013, D leased the said suspended period to the Defendant and used it for the production of aggregate from the Plaintiff’s site construction site of E’s logistics warehouse and auxiliary facilities (hereinafter “instant construction site”). The construction of the said suspended period to the Defendant on April 23, 2013, D leased it to the Defendant.

Upon entering into this contract, the plaintiff A representative director B refers to "A" and the defendant representative director J refers to "B" and the contract for the lease of the Offset period is concluded as follows:

Article 2 (Rent) (1) Rent/month: 42,00,000,000/VAT 2) 12 months of 12 months, the rent shall be paid only for 11 months of 12 months.

- The rent shall not be paid in January of each year of non-payment.

Article 3 (Conditions 1) The monthly rent shall be paid in the same manner as that of the previous LAD and the terms of payment. 2) The time of payment of rent shall be determined by the consultation between A and B.

Article 4 (Period of Contract) (1) As of the date on which a report on crushing is accepted; 2) as of the extension of permission, the term of the contract shall be automatically extended up to the date on which the production of aggregate is possible.

Article 10 (Special Terms and Conditions) 4 Measures taken by Administrative Authorities or "B".